Scope of work:

Site Installation, residential, Offices &  Workshops Excavation & Concrete work of unit Nos.5 & 6 of Powerhouse.

Excavation & Concrete works Draft-Tubes Nos. 4 & 5 & 6.

Excavation in Transformer Cavern Nos. 6 & 5 & 4.

Anchoring works in PowerHouse & Transformer Caverns.

 More than 16 km of monobar installation till now.

Excavation of 4 shafts using Raise Climber (Alimak).

Excavation, supporting and concreting of drainage shaft (50 meters height).

Construction of carpentry workshop with around 1000  m² of area and advanced equipment.

Construction of Residential places for more than 400 people.

Construction of more than 1000 m²  offices.